Skip to main content

Wrapping up the framing - Plumbing and HVAC

 


Garage is open and now that the framing is done they uncovered the windows. The final awnings were being built.


Final set of awnings are now over the garage. Blue roofing material went on parts of the roof this week. I imagine it should be done by the end of next week. 


We showed up and found a bunch of mechanical heating/cooling equipment in the garage early in the week.


We changed the stain color for our beams to Dark Oak with the tongue and groove being stained at 50% of the same color so we have some contrast.


More of the roof.


Most recent photo of the front of the house.


Back porch is done. See the pictures below for the process.








Picture from the inside with the upper wall still open.


Picture from the upstairs bedroom looking into the backyard and onto the new pack patio/porch.




Chimney was added!








Heating/cooling and plumbing coming along nicely below the house. In the crawl space it is clear that they've been working but not much to show in the actual house as of yet.



Tongue and groove arrived.


Water heater and furnace area in the garage starting to show evidence of progress. Yellow gas lines and copper pipes.


Gas lines for the stove and going up to the upstairs mechanical closet.


Guest bath shower roughed in.


Bags of mechanical stuff


Vents for registers showed up. They've since covered them all up with boards to keep dust and other garbage from falling into them.


Bathrooms are starting to have the hot and cold copper pipping.




Master shower with hot and cold pipes.


We met with our builder to go over some design ideas earlier this week. We picked out flooring and tile, sort of  a pre-order selection - to make sure we're good on price and all that. She will submit all of that to the flooring company and they will go double check measurements etc. and give us a final cost in a week or two. Once that is in we will finalize our plumbing fixtures and everything else once we make sure it all matches. The order will be placed AFTER we confirm everything else. 

We have two other meetings coming up. Our builder has sent us her ideas of the cabinets and for the most part there was little to add or change. We will go over the cabinets with the cabinet maker at some point soon. Also, the electrical walk through is planned for 2 weeks out. We wanted to do it sooner but we're out of town when the builder/electrician can do it and they are out of town when we can do it so he will start working on things that have to be done due to code or other regulations until we can meet and finalize things like plugs and light switches. 



Popular posts from this blog

Stem Walls and Windows

  They poured the concrete into the forms early last week and took them off within a day. They then came back and cleaned up the job site and let the concrete cure for the rest of the week. I love the view here facing that sunset! While we were waiting for the concrete to cure we met with our builder and the distributor that they use for their windows and exterior doors. They had bid out the windows based on the plans and we were meeting to go over everything and clarify questions. Before the meeting I reviewed the plans and compared it to the bid and found that they had missed one of windows in a guest bathroom and the bid had mentioned that two windows shown on the elevation plans were not on the actual floor plans and so we had to be pretty thorough. They had the windows drawn in as casement windows but in my mind I had always imagined single hung windows. I didn't know what these were called but I visited the  Anderson Windows website  and as I looked around I found o...

Backfilling

  Not a ton to report this week. They are working on backfilling. They have to backfill the garage with compactable soil and will then pour the slab in the garage. They also have to fill the areas where we will have our front porch and back patio with the compactable soil but the rest of the stuff can be backfilled with regular soil. Here are some pictures of the progress.  You can't really tell from this picture above, but there is quite a slope down from the house into the back yard and I'm going to have to figure out how to landscape that... The weather was spring-y and crappy this last week so I thought the blue sky was a nice one to end on. The weather is supposed to change from 50's and rainy to the 70's and sunny come April so we are looking forward to that! This last picture is the most recent one from earlier today. 

Cranes and Trusses

  The crane was scheduled for Tuesday so on Monday they got things ready.  Early Tuesday morning they were cranking. Here's the crane from far away. The crane in action.  View of the back dinning room. Great room with trusses. Great room as seen from the entry way.  The upstairs bedrooms were done with this little perch of what became a hallway. This is the "before" so you can appreciate the after. They put the trusses on the upstairs bedrooms over the entryway and you can see that below.  Trusses over the main living area and some of the trusses over the garage where there is some more living space. The crane was rented for 5 hours on Tuesday and this is what they got done. They will get the crane again this week and they are hoping to be done with the trusses at that point.  They put up the front, east facing, wall of the hallway. Same thing from inside the garage. Back, west facing, wall of the hallway was done. Starting to push out over the garage. This...