Skip to main content

Wrapping up the framing - Plumbing and HVAC

 


Garage is open and now that the framing is done they uncovered the windows. The final awnings were being built.


Final set of awnings are now over the garage. Blue roofing material went on parts of the roof this week. I imagine it should be done by the end of next week. 


We showed up and found a bunch of mechanical heating/cooling equipment in the garage early in the week.


We changed the stain color for our beams to Dark Oak with the tongue and groove being stained at 50% of the same color so we have some contrast.


More of the roof.


Most recent photo of the front of the house.


Back porch is done. See the pictures below for the process.








Picture from the inside with the upper wall still open.


Picture from the upstairs bedroom looking into the backyard and onto the new pack patio/porch.




Chimney was added!








Heating/cooling and plumbing coming along nicely below the house. In the crawl space it is clear that they've been working but not much to show in the actual house as of yet.



Tongue and groove arrived.


Water heater and furnace area in the garage starting to show evidence of progress. Yellow gas lines and copper pipes.


Gas lines for the stove and going up to the upstairs mechanical closet.


Guest bath shower roughed in.


Bags of mechanical stuff


Vents for registers showed up. They've since covered them all up with boards to keep dust and other garbage from falling into them.


Bathrooms are starting to have the hot and cold copper pipping.




Master shower with hot and cold pipes.


We met with our builder to go over some design ideas earlier this week. We picked out flooring and tile, sort of  a pre-order selection - to make sure we're good on price and all that. She will submit all of that to the flooring company and they will go double check measurements etc. and give us a final cost in a week or two. Once that is in we will finalize our plumbing fixtures and everything else once we make sure it all matches. The order will be placed AFTER we confirm everything else. 

We have two other meetings coming up. Our builder has sent us her ideas of the cabinets and for the most part there was little to add or change. We will go over the cabinets with the cabinet maker at some point soon. Also, the electrical walk through is planned for 2 weeks out. We wanted to do it sooner but we're out of town when the builder/electrician can do it and they are out of town when we can do it so he will start working on things that have to be done due to code or other regulations until we can meet and finalize things like plugs and light switches. 



Popular posts from this blog

Foundations

 One of the things I really want is a big, open garage. We planned it all out in the drawings but recently we heard back from the structural engineer that they will have to put a post/column in the middle of the garage. We talked with our builder about what could be done. She asked about a bigger truss but the truss guy says that they can't build a bigger truss.  We decided to pay the engineer to do the math and see if a large steel beam could be used because according to our builder she doesn't expect the beam to add that much cost, if its possible.  The engineer is currently working on seeing if its possible. If it is possible they will likely have to make the footings bigger and that would add concrete cost but overall the cost can't be predicted until the engineer updates his plans. Once the plans are updated our builder can let us know about costs and at that point we can decide if the increase cost is worth it or not.  I feel that paying an engineer a little mo...

Cranes and Trusses

  The crane was scheduled for Tuesday so on Monday they got things ready.  Early Tuesday morning they were cranking. Here's the crane from far away. The crane in action.  View of the back dinning room. Great room with trusses. Great room as seen from the entry way.  The upstairs bedrooms were done with this little perch of what became a hallway. This is the "before" so you can appreciate the after. They put the trusses on the upstairs bedrooms over the entryway and you can see that below.  Trusses over the main living area and some of the trusses over the garage where there is some more living space. The crane was rented for 5 hours on Tuesday and this is what they got done. They will get the crane again this week and they are hoping to be done with the trusses at that point.  They put up the front, east facing, wall of the hallway. Same thing from inside the garage. Back, west facing, wall of the hallway was done. Starting to push out over the garage. This...