Skip to main content

A slow 2 weeks...Garage slab was poured


Well, these last two weeks were rather boring. They finished backfilling and then they compacted the garage area and the area for the front porch and back patio with a special compactable soil. 

They then put some gravel and rebar in the garage area preparing it for the slab to be poured. Then, it sat for about a week.


Garage compacted


Front porch compacted


Back patio compacted


Garage with gravel and rebar

We'd drive by every day and see nothing, which was disappointing and a little frustrating. Then, one morning after dropping my son off for school I swung by the property and saw the trucks and guys working. I stood and watched them work for a while. I'm sure they thought I was crazy. It was about 40 degrees, SUPER windy, which makes the cold a million times worse and I was in a t-shirt and basketball shorts. I always appreciate watching people do a good job at whatever they are trained to do. These guys worked fast and as a team. I chatted with them for a bit and then had to get home and get back to what I needed to get done.


I was happy to see one truck. 


When the other one showed up and they were pouring at the same time I was pretty impressed with the teamwork from these guys.


They had a really cool way of getting the grade.  They had big nails with "L" shaped brackets secured to them at a certain height and the bracket fit right into a long aluminum thing in the shape of a 2x4 that was about 10 feet long.


Before even half of the concrete had been poured they were working on smoothing it out. 


Started turning white as it dried out.




A day later they came back and cut some lines in the concrete.


This was 5 days ago. No news on the next steps. Lumber should be next and framing but we have started looking at fixtures for plumbing so they can start to frame it out correctly. 

Hopefully they'll start the framing soon. We were told the framers that our general contractor uses are the best in the area but that they were a few weeks out. This was back at the time we met to order our windows and exterior doors so maybe in the next week or two. I'm hoping! When not much goes it feels like things are dragging out from day to day, which made the last 2 weeks, a slow 2 weeks!






 

Popular posts from this blog

Wrapping up the framing - Plumbing and HVAC

  Garage is open and now that the framing is done they uncovered the windows. The final awnings were being built. Final set of awnings are now over the garage. Blue roofing material went on parts of the roof this week. I imagine it should be done by the end of next week.  We showed up and found a bunch of mechanical heating/cooling equipment in the garage early in the week. We changed the stain color for our beams to Dark Oak with the tongue and groove being stained at 50% of the same color so we have some contrast. More of the roof. Most recent photo of the front of the house. Back porch is done. See the pictures below for the process. Picture from the inside with the upper wall still open. Picture from the upstairs bedroom looking into the backyard and onto the new pack patio/porch. Chimney was added! Heating/cooling and plumbing coming along nicely below the house. In the crawl space it is clear that they've been working but not much to show in the actual house as of yet. T...

Finished framing! Plumbing, HVAC and electrical...

This was just a cool picture from a lightning storm up at the property.  HVAC stuff began getting installed. Exposed beams for the grand room prepped and ready for installation. Supports for above the beam are in place. Center main beam is ready to go. Front timbers done. Back timbers done. Blue roofing base is on most of the house at this point. More HVAC vents installed. Toilet mounts ready to go. Cedar posts on the awnings. Beautiful sunset. More vents installed. BEAMS ARE UP!!! View from the entry way with the fireplace and beams in place. Tongue and groove (T&G) installed in the front. Other half of the porch T&G installed. Electrical stuff getting done. T&G done on half of the back porch. Tubs arrived for the upstairs bathrooms. Plumbing for the tubs is done.  Back porch with T&G. View from the front door with the T&G done. View of the front porch with the T&G. Vents from the bathrooms up to the roof.  Upstairs plumbing coming along.  Ve...

Foundations

 One of the things I really want is a big, open garage. We planned it all out in the drawings but recently we heard back from the structural engineer that they will have to put a post/column in the middle of the garage. We talked with our builder about what could be done. She asked about a bigger truss but the truss guy says that they can't build a bigger truss.  We decided to pay the engineer to do the math and see if a large steel beam could be used because according to our builder she doesn't expect the beam to add that much cost, if its possible.  The engineer is currently working on seeing if its possible. If it is possible they will likely have to make the footings bigger and that would add concrete cost but overall the cost can't be predicted until the engineer updates his plans. Once the plans are updated our builder can let us know about costs and at that point we can decide if the increase cost is worth it or not.  I feel that paying an engineer a little mo...