Skip to main content

Foundation Prep




The soil on our lot was not great for a foundation so we had to dig a deep hole and then back fill it with soil that can compact well enough to support the house. We had to put 3 feet of backfill in! We watched them bring load after load of dirt and then smooth it out and compact it and then do it all over again until the full 3 feet were filled in. Last night I took my daughter up there after soccer practice and we walked around on the final grade. Footings and forms should be going up next week!





Popular posts from this blog

Wrapping up the framing - Plumbing and HVAC

  Garage is open and now that the framing is done they uncovered the windows. The final awnings were being built. Final set of awnings are now over the garage. Blue roofing material went on parts of the roof this week. I imagine it should be done by the end of next week.  We showed up and found a bunch of mechanical heating/cooling equipment in the garage early in the week. We changed the stain color for our beams to Dark Oak with the tongue and groove being stained at 50% of the same color so we have some contrast. More of the roof. Most recent photo of the front of the house. Back porch is done. See the pictures below for the process. Picture from the inside with the upper wall still open. Picture from the upstairs bedroom looking into the backyard and onto the new pack patio/porch. Chimney was added! Heating/cooling and plumbing coming along nicely below the house. In the crawl space it is clear that they've been working but not much to show in the actual house as of yet. T...

Finished framing! Plumbing, HVAC and electrical...

This was just a cool picture from a lightning storm up at the property.  HVAC stuff began getting installed. Exposed beams for the grand room prepped and ready for installation. Supports for above the beam are in place. Center main beam is ready to go. Front timbers done. Back timbers done. Blue roofing base is on most of the house at this point. More HVAC vents installed. Toilet mounts ready to go. Cedar posts on the awnings. Beautiful sunset. More vents installed. BEAMS ARE UP!!! View from the entry way with the fireplace and beams in place. Tongue and groove (T&G) installed in the front. Other half of the porch T&G installed. Electrical stuff getting done. T&G done on half of the back porch. Tubs arrived for the upstairs bathrooms. Plumbing for the tubs is done.  Back porch with T&G. View from the front door with the T&G done. View of the front porch with the T&G. Vents from the bathrooms up to the roof.  Upstairs plumbing coming along.  Ve...

Foundations

 One of the things I really want is a big, open garage. We planned it all out in the drawings but recently we heard back from the structural engineer that they will have to put a post/column in the middle of the garage. We talked with our builder about what could be done. She asked about a bigger truss but the truss guy says that they can't build a bigger truss.  We decided to pay the engineer to do the math and see if a large steel beam could be used because according to our builder she doesn't expect the beam to add that much cost, if its possible.  The engineer is currently working on seeing if its possible. If it is possible they will likely have to make the footings bigger and that would add concrete cost but overall the cost can't be predicted until the engineer updates his plans. Once the plans are updated our builder can let us know about costs and at that point we can decide if the increase cost is worth it or not.  I feel that paying an engineer a little mo...