I got my hot/cold hose bib in the garage. Other hose bibs around the house. Laundry room vents and plumbing roughed in. Electrical started. We met with our cabinet guy last week and our electrician earlier this week. Once the cabinetry was finalized the electrician put the cabinet plans everywhere so they know what to plan for. We did a 2 and a half hour walk through with our electrician this week and the next day he got to work. We planned switches and plugs and talked light placement and all that fun stuff. Here's to hoping we don't regret our decisions and wish we had put a plug somewhere or gotten rid of a light switch in one of the halls or something like that. Double stackable laundry cabinets. Electrical work getting done. Also, the fireplace kit was delivered. Should be getting installed this week! We meet with our flooring people again this coming week to finalize our flooring options. Exciting stuff.
This was just a cool picture from a lightning storm up at the property. HVAC stuff began getting installed. Exposed beams for the grand room prepped and ready for installation. Supports for above the beam are in place. Center main beam is ready to go. Front timbers done. Back timbers done. Blue roofing base is on most of the house at this point. More HVAC vents installed. Toilet mounts ready to go. Cedar posts on the awnings. Beautiful sunset. More vents installed. BEAMS ARE UP!!! View from the entry way with the fireplace and beams in place. Tongue and groove (T&G) installed in the front. Other half of the porch T&G installed. Electrical stuff getting done. T&G done on half of the back porch. Tubs arrived for the upstairs bathrooms. Plumbing for the tubs is done. Back porch with T&G. View from the front door with the T&G done. View of the front porch with the T&G. Vents from the bathrooms up to the roof. Upstairs plumbing coming along. Ve...